Time and Cost Control on Construction Projects
- Deep Parikh

- Mar 18, 2021
- 4 min read
Objectives:
Project cost and time management techniques
Establish a work activity list
The sequence of work activities
Cost control issues and methods
Time and Cost Control on Construction Projects
The major parameters on any project are cost and duration. Any contractor must control these. The contractor is committed to completing the project in the specific time frame and at a finite cost. For this, project information must be collected in real-time so that informed decisions can be made to modify operations to meet the time frame and estimated cost.
Traditionally, the contractor’s field personnel, with their skills and knowledge executed the project with minimal cost. The effectiveness of control of time and cost on the construction projects was only evident at the end of the project based upon profitability achieved and if the job was completed on time.
In recent years, however, the use of technology, mobile Apps, and computerized cost control tools, provide visibility of project at any given time and provide a means of monitoring the effectiveness of the controls during a project. This allows project site teams to adjust to understand labour productivity and subcontractor efficiency daily, and helps bring the project progress within budget.
Small as well as large construction projects can benefit from such construction technology tools to monitor time and cost control. It is no longer a luxury to purchase these technology tools. For a few hundred rupees, less than the cost of an employee, labour and material cost control techniques can be implemented during the construction execution.
1.Project Time (Schedule) Control (Ref. Constructskills: https://youtu.be/Kl9f6nEk8io)
The construction project owner will always need a project to be completed at earliest, to save on fixed and overhead costs, improving profitability. There are also liquidated damages which need to be avoided.
The completion date is often based on the owner’s need for the facility and not practically expected construction duration.
A project needs to be planned according to construction sequence and realistic projected duration of activities, for efficient planning, procurement, and execution. The planning of work activities must consider the following:
List / Identify all work activities
Duration of activities
Sequencing of activities
Interrelationship of the activities
Adequate skilled/unskilled crafts requirements
Material delivery dates
This information could be compiled jointly by all the personnel deployed on the project site, to get their buy-in and better updates of project schedules as work progresses. 2.Identification of activities Each activity should be identified with the following details:
Each activity should be a separate function and linked to a Bill of Quantity (BoQ) item
Each activity should be able to be linked to the craft team
Each activity should have the ability to capture budget vs actual costs
Activity duration should be no shorter than one day.
3.Sequence of activity
The construction managers should sequence the activities considering the following:
Discuss reasons with the team for choosing one sequence over another.
Compare durations and costs associated with different sequences.
Consider the time required for procurement, curing, setting, etc.
4.Duration of activity
When determining the duration of a construction activity you should consider these factors:
Should be linked with labour hours and methodology of execution of the activity.
Should be related to the quantity of work accomplished.
Consider the number of workdays and work hours/workday.
Weather and site conditions
Procurement of material
5.The project schedule
It is a communication tool to share among the project team. The basic information contained in is a good schedule is:
Start date required on Jobsite and duration allowed for work.
Current status of the project
Constraints: Date drawings and/or material due at Jobsite.
Use of software tools such as MS Project or Primavera. These technology tools normally calculate the critical path for the project.
Updating the project is necessary periodically, either weekly or biweekly. A baseline schedule must be saved to compare the progress to the original plan. Completion date changes should be infrequent. If end dates changes, it should be properly communicated among project participants. 6.Project Cost Control Comparison of the actual cost with the budgeted cost during the project provides an accurate measurement of the success of the construction project. Several computer software programs are available for capturing actual labour and material costs incurred in real-time cost control. The software easily helps capture site data and computes the data such as reconciliations of material, labour productivity, and quality issues. The primary objective in using construction management software tools is setting up a project cost control system that can be used to collect, collaborate, collaborate and report construction cost activities. The cost collected should be at BoQ item level, so that identifications of a problem is easy and helps in finding a solution. Following points needs to be considered while creating a cost control system:
Cost collected can be used for productivity analysis
Comparison of budget vs. actual should be in real-time
Feedback system regarding labour productivity assessment should be possible
Factors related to inefficiencies should be traced to each activity
There are several problems related to low productivity at sites. Some examples are:
Poor Layout of material storage areas, skills and experience of crafts, improper sequencing, wrong or not enough tools, tackles, and equipment, insufficient or defective material, weather conditions, improper supervisions and much more.
Software tools help collect data and prompt identification of reasons for low productivity is possible.
Looking for Construction Management software to Improve Your Employees Efficiency? Check out the best Construction Management software solutions.
ProCost Systems - Digitize Construction
Reference: Andrew D. F. Price, Alan Bryman, And Andrew R. J. Dainty, Member, ASCE 2004 article on Leadership and Management





https://dn88.site/da-ga-dn88/ bữa mình thấy bạn bè nhắc nên tiện tay mở thử cho biết, chủ yếu xem trang họ trình bày ra sao thôi chứ không ngồi đọc hết nội dung. Ấn tượng đầu là bố cục nhìn khá thoáng, chữ không bị dồn dập nên lướt nhanh cũng đỡ mỏi mắt. Mình có liếc qua khối “BÀI VIẾT MỚI” thấy họ để dạng danh sách nên dễ nắm hôm nay có gì mới, kiểu nhìn một phát là hiểu. Với lại cái menu danh mục đặt ngay chỗ dễ thấy, bấm qua lại mấy mục cũng không bị rối. Nói chung cảm giác như đang xem một trang tổng hợp tin/giải trí, gọn gàng vừa đủ. Mình thích nhất…
abc8 mình ghé thử vì đang cần xem nạp tiền làm sao cho nhanh, tưởng đâu rối mà đọc lại thấy khá dễ theo. Trang viết kiểu chia đoạn ngắn, có tiêu đề rõ nên lướt xuống là bắt được ý chính liền, không bị chữ dồn một cục. Mình để ý họ nói về Internet Banking khá gọn, kiểu liên kết nhiều ngân hàng lớn nên thao tác nhìn có vẻ quen tay với ai hay chuyển khoản. Ngoài ra có nhắc thêm ví điện tử như Momo, ZaloPay, ViettelPay nên ai không thích dùng ngân hàng cũng có lựa chọn. Nói chung cảm giác họ trình bày để người mới khỏi phải đoán mò, đọc vài phút là…
https://apptaixiu.io/ mình lướt thử vì thấy bạn bè nhắc hoài, kiểu vào xem giao diện với cách họ viết thôi. Cảm giác đầu tiên là trang này chia nội dung theo chủ đề khá dễ theo, không bị một mớ chữ dài lê thê. Mình đọc lướt vài đoạn thấy họ có nhắc đến chuyện bảo mật kiểu SSL 256-bit ngay trong bài, nên nhìn cũng “có đầu có đũa” hơn mấy trang nói chung chung. Điểm mình thích là chữ rõ, nền gọn, kéo xuống không bị rối mắt. Mấy tiêu đề dạng “top 8 app” đặt nổi bật, bên dưới tách thành từng khối nội dung riêng nên nhìn phát biết đang ở phần nào của trang.
Mấy hôm nay thấy bạn bè bàn về nổ hũ nên mình cũng tiện tay vào xem thử trang NOHU họ làm giao diện ra sao. Mình không đọc sâu, chỉ lướt kiểu xem bố cục với cách họ ghi thông tin có rõ ràng không. Đang kéo giữa trang thì thấy có đoạn họ nhắc RTP ổn định trên 96%, nhìn cũng đỡ kiểu nói mơ hồ. Mình vào bằng link này https://nohu9078.club/ rồi nghía qua một vòng, cảm giác trang tải khá nhanh, chữ không bị dồn dập nên mắt dễ chịu. Mấy mục tiêu đề được chia thành từng khối riêng, kéo xuống là biết mình đang ở phần nào chứ không bị lạc. Nói chung phần…
thedriftboss.com was one of those sites I landed on while killing time, and I ended up sticking around longer than I expected. The first thing I noticed is the game sits right up front and doesn’t make you dig through a bunch of clutter to get going. I’m not even that deep into drifting games, but the whole one-button control thing is explained in a super quick way, so it’s easy to understand without reading a wall of text. The page itself feels pretty chill to scroll through—nothing flashy or annoying jumping in your face. Also nice that it runs smoothly on my phone without feeling cramped. The headings and little info blocks under the main game area are laid…